Metallium Advances Texas Facility Development with Key Equipment
Orders, Site Upgrades, and Feedstock Purchase
KEY PROGRESS MILESTONES
▪ Equipment Procurement – Orders placed for key e-waste pre-processing systems (size reduction, preheating,
material handling) and site infrastructure (mobile offices) with additional long-lead items already ordered.
▪ Site Readiness Advancing – Electrical upgrades, site clearing, drainage improvements, and mobile offices in place.
▪ Environmental & Compliance Leadership – VaporPoint engaged for best-practice air and water quality systems.
▪ Commissioning Feedstock Locked In – 60 tonnes of metal-rich PCB E-Waste ordered, de-risking start-up.
▪ Proven Technology Performance1 from U.S.-sourced e-waste feedstocks:
⎯ Gold – 100% recovery from e-waste feedstock* grading 551 g/t Au, over 100x higher than typical primary ores.
⎯ Silver – 97% recovery at 2,804 g/t Ag.
⎯ Antimony – 98% recovery from feedstock grading 3.13% Sb.
▪ Expansion Pipeline – Actively progressing opportunities for additional pre-permitted sites near major e-waste
collection centres to support rapid U.S. rollout.
*Grades of e-waste that has had plastics removed via separate pretreatment process (see ASX: MTM announcements 03 June 2025, 10 April 2025)
Metallium Limited (“Metallium” or the “Company”) (ASX: MTM; OTCQX: MTMCF) is pleased to report substantial
progress on its Technology Campus in Chambers County, Texas – the site of its first commercial Flash Joule Heating
(FJH) metal recovery plant in the United States.
Since securing its Chambers County, Texas site, Metallium has significantly progressed the redevelopment of the site
infrastructure to enable commissioning to commence in December 2025. Alongside equipment procurement and site works,
a wide range of preparatory activities are now underway or completed:
•
•
•
•
•
•
•
Permitting & Compliance – Advancing air quality, water quality, and waste management permitting; engaged
VaporPoint to implement best-practice monitoring and compliance systems.
Engineering – Finalising balance-of-plant engineering, structural analysis, and integration design. Metallium has
engaged tier-one engineering firm Hunt, Guillot & Associates (HGA) for plant integration, implementation
engineering, and structural assessments.
Utility & Infrastructure Engagement – Working with the local power utility Entergy Texas to finalise supply
arrangements and capacity for long-term operations.
Waste Management Agreements – In discussions with an adjacent landfill operator to establish solids residue
discharge pathways in compliance with all environmental regulations.
Team Buildout – Recruiting key personnel, including U.S. CFO, plant manager, engineering leads, and business
development staff to support operations and growth.
Business Development & Feedstock Pipeline – Pursuing commercial opportunities across a range of critical metal
feedstocks, including antimony, rare earth element (REE) magnets, heavy REE-enriched e-scrap, and selected
mining concentrates.
On-site works are advancing, with electrical system upgrades, site clearing, and drainage improvements already
underway. These works are designed to optimise the facility for safe, efficient operation.
A key commissioning milestone has also been achieved with the order of 60 tonnes of printed circuit board (PCB) scrap
“e-waste”. This batch has been selected to closely match the anticipated long-term feedstock profile for the facility, allowing
process tuning and operational readiness testing under realistic operating conditions.
1
ASX: MTM announcements on e-waste recovery testwork dated 03 June 2025 & 10 April 2025. Also, see earlier reports dated: 08 October 2024, 25 September 2024, and 12 September 2024.
ENGAGE WITH THIS ANNOUNCEMENT ON INVESTORHUB: HERE
ASX: MTM | OTCQX: MTMCF
Metallium Managing Director & CEO, Michael Walshe, commented: “We are progressing on all fronts to deliver our first
U.S. facility as planned. With critical equipment ordered, site works advancing, and commissioning feedstock secured, the
project is materially de-risked.
“In parallel, we are executing the detailed integration work with resources from HGA, strengthening our environmental
systems with specialised advice from VaporPoint, and finalising utility and waste management arrangements. Our
recruitment drive ensures we have the technical and operational capability to move quickly from commissioning to full
production.
“Our ambition is to leverage the FJH modular system design so that we can rapidly expand this model across the United
States, targeting pre-permitted sites strategically located near major e-waste collection centres. Every step we are taking
now, from engineering to feedstock readiness, is about building a robust, scalable platform capable of processing a diverse
range of critical and precious metals, positioning Metallium as a leader in U.S.-based metals recovery and refining”.
The Company will continue to update shareholders as construction, installation, and commissioning milestones are
achieved.
Figure 1: Metallium’s Chambers County, Texas Technology Campus – Front Entrance. Facility undergoing upgrades ahead
of December 2025 commissioning
This announcement has been authorised for release by the Board of Directors.
2
ASX: MTM | OTCQX: MTMCF
For further information, please contact:
Michael Walshe
Managing Director & CEO
Metallium Ltd
info@MetalliumInc.com | +61 8 6391 0112
Andrew Keys
Investor Relations & Corporate Communications
Keys Thomas Associates
Andrew.keys@keysthomas.com | +61 400 400 380
ABOUT METALLIUM LIMITED
Metallium Ltd (ABN 27 645 885 463), is pioneering a low-carbon, high-efficiency approach to recovering critical and precious metals
from mineral concentrates and high-grade waste streams. The company’s patented Flash Joule Heating (FJH) technology enables the
extraction of high-value materials—including gallium, germanium, antimony, rare earth elements, and gold—from feedstocks such as
refinery scrap, e-waste, and monazite.
Aligned with U.S. strategic supply chain objectives, Metallium has recently secured its first commercial site in Texas via its wholly owned
subsidiary, Flash Metals USA Inc., marking a major step toward near-term production and revenue generation.
.
To learn more, visit:
Website:
metalliuminc.com
Contact:
info@metalliuminc.com
Investor Hub:
investorhub.metalliuminc.com
𝕏
x.com/Metallium_MTM
|
+61 8 6391 0112
www.linkedin.com/company/metalliumltd
USA Office:
12 Greenway Plaza, Suite 1100, Houston, Texas USA 77046
Australia Office:
Unit 4, 22 Railway Road, Subiaco, Western
3
ASX: MTM | OTCQX: MTMCF
CAUTIONARY STATEMENT REGARDING VALUES & FORWARD-LOOKING INFORMATION
The figures, valuations, forecasts, estimates, opinions and projections contained herein involve elements of subjective judgment and
analysis and assumption. Metallium does not accept any liability in relation to any such matters, or to inform the Recipient of any matter
arising or coming to the company’s notice after the date of this document which may affect any matter referred to herein. Any opinions
expressed in this material are subject to change without notice, including as a result of using different assumptions and criteria. This
document may contain forward-looking statements. Forward-looking statements are often, but not always, identified by the use of words
such as “seek”, “anticipate”, “believe”, “plan”, “expect”, and “intend” and statements than an event or result “may”, “will”, “should”,
“could”, or “might” occur or be achieved and other similar expressions. Forward-looking information is subject to business, legal and
economic risks and uncertainties and other factors that could cause actual results to differ materially from those contained in forwardlooking statements. Such factors include, among other things, risks relating to property interests, the global economic climate, commodity
prices, sovereign and legal risks, and environmental risks. Forward-looking statements are based upon estimates and opinions at the
date the statements are made. Metallium undertakes no obligation to update these forward-looking statements for events or
circumstances that occur subsequent to such dates or to update or keep current any of the information contained herein. The Recipient
should not place undue reliance upon forward-looking statements. Any estimates or projections as to events that may occur in the future
(including projections of revenue, expense, net income and performance) are based upon the best judgment of Metallium from
information available as of the date of this document. There is no guarantee that any of these estimates or projections will be achieved.
Actual results will vary from the projections and such variations may be material. Nothing contained herein is, or shall be relied upon as,
a promise or representation as to the past or future. Metallium, its affiliates, directors, employees and/or agents expressly disclaim any
and all liability relating or resulting from the use of all or any part of this document or any of the information contained herein.
4
Share your feedback
Discover