COMMENCEMENT OF COMMISSIONING AT TEXAS TECHNOLOGY
CAMPUS FOLLOWING SUCCESSFUL FIRST CHLORINE FLASH
Metallium Limited (“Metallium” or the “Company”) (ASX: MTM; OTCQX: MTMCF) announces that commissioning has
formally commenced at its Texas Technology Campus (“Gator Point”) in Chambers County, Texas, following the
successful and safe completion of the first chlorine flash using the Company’s proprietary Flash Joule Heating (FJH)
technology. This milestone represents a major step in de-risking the Company’s U.S.-based critical-metals recovery
platform, with commissioning activities progressing in parallel with ongoing construction works to support future expansion.
HIGHLIGHTS:
Texas Technology Campus – Commissioning Successfully Commenced on Schedule
▪ First chlorine flash successfully completed on the FJH system, safely and in line with design expectations.
▪ Commissioning has commenced on schedule, consistent with prior guidance.
▪ Represents the first integrated operation of the FJH–chlorination process at the Texas Technology Campus.
Demonstration Line Operational:
▪ A three-crucible FJH demonstration line has completed both dry and wet commissioning.
▪ The demonstration line is now fully operational and will be used on an ongoing basis for feedstock qualification,
process optimisation, customer and partner testing programs.
▪ Provides a dedicated R&D and scale-up platform alongside commissioning of the wider facility.
Key Environmental Permit Secured:
▪ Texas Commission on Environmental Quality (TCEQ) Permit-by-Rule (PBR) approved on 5 December 2025.
▪ The permit provides a key regulatory milestone and enables commissioning and operations to proceed.
Commissioning Underway Across the Wider Plant:
▪ Commissioning activities are progressing across the broader Texas Technology Campus, including:
o Utilities and electrical systems; Feedstock preparation and handling circuits.
o Environmental control and gas-scrubbing systems; Process controls and safety systems.
▪ Commissioning will proceed through a structured program of dry and wet commissioning over the coming months.
Clear Scale-Up Pathway to Stage-1 Operations:
▪ Commissioning is aligned with Metallium’s staged ramp-up strategy toward Stage-1 nameplate capacity of 8,000
TPA of inbound printed circuit board (PCB) E-waste.
▪ Stage-1 throughput is targeted by Q3 2026, following progressive commissioning and modular expansion.
▪ Texas Technology Campus is designed to support parallel scale-up, customer testing and commercial deployment.
PCB and Specialty Metal Processing Focus:
▪ Stage-1 operations focused on recovery of gold, copper, silver and tin from PCB feedstocks.
▪ Advanced planning underway for a future gallium/germanium process line, subject to securing feedstock supply.
PCB Feedstock Supply:
▪ Advanced negotiations are underway for several long-term PCB feedstock supply agreements, with final
documentation at an advanced stage.
Metallium Managing Director & CEO Mr Walshe said: “The successful completion of our first chlorine flash is a defining
milestone for Metallium. It confirms that the core FJH process is operating as designed under real operating conditions and
marks the formal start of commissioning at Gator Point, exactly as planned.
“This milestone reflects an exceptional execution effort by the Metallium team and our contractors. Since acquiring the site,
the campus has undergone a substantial transformation, including major civil and concrete works, new building
construction, and the installation of complex process and environmental infrastructure. Delivering commissioning on
schedule is a credit to the discipline, commitment and capability of everyone involved.
2
ASX: MTM | OTCQX: MTMCF
“Having a three-crucible demonstration line already dry and wet commissioned gives us a powerful platform for ongoing
R&D, feedstock qualification and partner engagement while we commission the wider plant. Securing our TCEQ Permit-by-
Rule provides a key regulatory milestone and enables us to advance commissioning with confidence.
“In parallel, we are in advanced negotiations to secure long-term PCB feedstock supply arrangements to support Stage-1
operations. Securing high-quality, contracted feedstock is a critical pillar of our operating strategy as we scale toward 8,000
tonnes per annum of inbound PCB capacity.”
Fig. 1: Texas technology campus photos.
Fig. 2: Wet commissioning of the demonstration line at Gator Point.
3
ASX: MTM | OTCQX: MTMCF
TARGET PRODUCTS AND PROCESSING PATHWAY
Metallium’s initial commissioning and Stage-1 operations at the Texas Technology Campus are focused on the recovery of
high-value metals from printed circuit board (PCB) feedstocks. Target products from PCB processing include gold, copper,
silver and tin, with recoveries varying based on feed composition.
Recovered metals are produced via Metallium’s proprietary FJH process in the form of saleable metal chloride intermediates,
suitable for downstream refining and commercial offtake.
In parallel, Metallium is advancing plans to introduce a dedicated gallium and germanium processing line at the Texas
Technology Campus, subject to the finalisation of feedstock supply arrangements. Gallium and germanium are strategically
important semiconductor metals, and the modular design of the campus allows additional processing lines to be integrated
efficiently as supply chains are secured.
This staged approach enables Metallium to prioritise near-term PCB processing while retaining flexibility to expand into
higher-value specialty metals as supply becomes available.
Fig. 3: Primary focus metals.
TEXAS TECHNOLOGY CAMPUS OVERVIEW
The Texas Technology Campus has been developed as Metallium’s first U.S. commercial processing hub, designed to
support near-term operations, ongoing technology development, and scalable expansion.
Installed Processing and Site Infrastructure
The campus currently hosts, and is being developed to host, a combination of operational processing equipment, supporting
infrastructure and expansion-ready facilities, including:
• Flash Joule Heating (FJH) processing systems, including a demonstration line now fully dry and wet
commissioned, and designed to be replicated in modular form.
• Feedstock preparation and handling equipment, including shredding, size-reduction and material handling
systems suitable for PCB and other high-grade electronic waste streams.
• Environmental and emissions control systems, including gas-scrubbing, ventilation and containment
infrastructure aligned with TCEQ permitting requirements.
• Electrical, utilities and control systems, providing the backbone for staged commissioning, ramp-up and future
module integration.
• Laboratory and analytical capability, supporting metallurgical reconciliation, feedstock qualification and ongoing
process optimisation.
• Multiple industrial buildings and hardstand areas, enabling parallel operations, additional module installation and
future throughput expansion.
4
ASX: MTM | OTCQX: MTMCF
This configuration allows Metallium to commission, test and scale processing capacity in parallel, while maintaining
operational flexibility across multiple feedstock types.
Strategic Role of the Texas Technology Campus
The Texas Technology Campus is intended to serve as:
• Metallium’s U.S. anchor site for Build-Own-Operate (BOO) processing of high-value electronic waste and specialty
metal feedstocks.
• A technology demonstration and validation hub, supporting customer trials, partner engagement and downstream
commercial agreements.
• A blueprint for replication, informing the design and deployment of future U.S. and international sites using
standardised FJH modules.
• A platform to support technology licensing and processing-as-a-service models for mineral processing and
critical-metal recovery projects.
Located within a major U.S. industrial corridor, with direct access to logistics infrastructure, utilities and skilled labour, the
campus is strategically positioned to support domestic supply-chain reshoring objectives and rapid commercial scale-up.
As commissioning progresses, the site will transition from a commissioning and demonstration facility into a fully
operational commercial processing hub, underpinning Metallium’s broader strategy to establish a distributed network of
FJH-based recovery plants across key waste and mineral jurisdictions.
NEXT STEPS
• Continue staged dry and wet commissioning across the wider facility
• Progressive integration of additional reactor, feedstock and environmental systems
• Ongoing operation of the demonstration line for R&D and customer testing
• First product generation and metallurgical reconciliation campaigns
• Incremental scale-up toward 8,000 TPA Stage-1 PCB throughput by Q3 2026
STRATEGIC CONTEXT
The commencement of commissioning at the Texas Technology Campus positions Metallium among a limited group of
U.S.-based operators actively commissioning next-generation critical-metals recovery infrastructure.
The Gator Point facility underpins Metallium’s build-own-operate and technology-licensing strategy across:
• Urban mining and electronic waste
• Specialty and semiconductor metals
• Rare earth and mineral-processing applications
With commissioning underway, key permits secured, demonstration systems operational and feedstock agreements nearing
completion, Metallium continues to advance toward commercial operations and industrial-scale deployment of its FJH
technology in the United States and other priority jurisdictions.
This announcement has been authorised for release by the Board of Directors.
For further information, please contact:
Michael Walshe
Managing Director & CEO
Metallium Ltd
info@MetalliumInc.com | +61 8 6391 0112
Andrew Keys
Investor Relations
Keys Thomas Associates
Andrew.keys@keysthomas.com | +61 400 400 380
5
ASX: MTM | OTCQX: MTMCF
ABOUT METALLIUM LIMITED
Metallium Ltd (ABN 27 645 885 463), is pioneering a low-carbon, high-efficiency approach to recovering critical and precious metals
from mineral concentrates and high-grade waste streams. The company’s patented Flash Joule Heating (FJH) technology enables the
extraction of high-value materials, including gallium, germanium, antimony, rare earth elements, and gold, from feedstocks such as
refinery scrap, e-waste, and monazite.
Aligned with U.S. strategic supply chain objectives, Metallium has recently secured its first commercial site in Texas via its wholly owned
subsidiary, Flash Metals USA Inc., marking a major step toward near-term production and revenue generation.
To learn more, visit:
Website: metalliuminc.com
Contact: info@metalliuminc.com | +61 8 6391 0112
Investor Hub: investorhub.metalliuminc.com
𝕏 x.com/Metallium_MTM
www.linkedin.com/company/metalliumltd
USA Office: 12 Greenway Plaza, Suite 1100, Houston, Texas USA 77046
Australia Office: Unit 4, 22 Railway Road, Subiaco, Western Australia 6008
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION
Information included in this announcement constitutes forward-looking statements. Often, but not always, forward-looking statements can be identified by
the use of words such as “may”, “will”, “expect”, “intend”, “plan”, “estimate”, “anticipate”, “continue”, “guidance” or other similar expressions, and may
include, without limitation, statements regarding Metallium’s plans, strategies and objectives, commissioning activities, anticipated production or
construction timelines, processing capacity, and expected operational outcomes.
Forward-looking statements inherently involve known and unknown risks, uncertainties and other factors that may cause actual results, performance or
achievements to differ materially from those expressed or implied in such statements. Relevant factors may include, but are not limited to, operational
and technical risks, the availability and quality of feedstock, permitting and regulatory approvals, changes in commodity prices, foreign exchange
fluctuations, general economic conditions, supply-chain constraints, the ability to scale and commercialise technology, and changes to the regulatory or
operating environment.
Forward-looking statements are based on Metallium’s good-faith assumptions relating to the financial, market, regulatory and other relevant environments
that will exist and affect the Company’s business and operations in the future. The Company does not give any assurance that the assumptions on which
forward-looking statements are based will prove to be correct, or that the Company’s business or operations will not be affected in any material manner
by these or other factors not foreseen or foreseeable.
Although Metallium attempts to identify factors that could cause actual actions, events or results to differ materially from those disclosed in forward-
looking statements, there may be other factors that could cause actual results or outcomes not to be as anticipated, estimated or intended. Accordingly,
readers are cautioned not to place undue reliance on forward-looking statements. Forward-looking statements speak only as of the date of this
announcement. Subject to any continuing obligations under applicable law or relevant stock exchange listing rules, Metallium undertakes no obligation to
publicly update or revise any forward-looking statements.
Share your feedback
Discover