ASX Release 16 June 2026
Successful Completion of First Multi-Unit Flash Joule Heating Operations Campaign
HIGHLIGHTS:
▪ Three FJH units successfully operated simultaneously during a 12-hour operating campaign with above
expected availability and utilisation results
▪ 18 successful batches completed and approximately 0.3 tonnes of inert material processed during the campaign
▪ Operating throughput achieved was broadly consistent with processing reactor feed volumes derived from
several tonnes per day of incoming commercial feedstocks following preprocessing and upgrading
▪ 83% availability and approximately 100% utilisation achieved during active operation of three FJH units running
simultaneously, providing confidence in the robustness and scalability of the FJH operating platform.
▪ Campaign completed without any safety incidents and with zero lost-time injuries (LTI)
▪ Critical operating, instrumentation, controls and engineering data generated to support future scale-up
activities
Metallium Limited (“Metallium” or the “Company”) (ASX: MTM; OTCQX: MTMCF; OTCQX ADR: MTLMY) is pleased to
announce the successful completion of its first multi–Flash Joule Heating (FJH) Reactor-unit ‘hot’ commissioning
campaign at the Company's technology development facility in Texas. The campaign was designed to evaluate sustained
operation of multiple FJH reactors running in parallel and represents an important milestone in the scale-up and
commercial development of the Company's proprietary FJH technology platform.
Table 1: Campaign Performance Metrics
Metric Result
Active FJH Units 3
Campaign Duration 12 Hours
Successful Batches 18
Material Processed in Reactors ~0.3 tonnes*
Availability 83%
Utilisation ~100%
Safety Incidents 0
Lost Time Injuries 0
Important Scale-Up Milestone: Commercial deployment of FJH technology is expected to involve multiple reactor units
operating in parallel. Successful operation of three units simultaneously under sustained operating conditions represents a
significant engineering milestone in advancing the technology from laboratory-scale validation toward demonstration-scale
deployment. The campaign successfully demonstrated:
• Sustained multi-unit operation over a full operating shift with an impressive 83% availability and near 100%
utilisation factor
• Stable fluidisation and material handling across multiple operating trains.
• Coordinated operation of three independent processing trains with our complete 12-person team encompassing
engineers, operators and safety personnel.
• Repeatable batch processing, operating procedures & reliability of mechanical systems under extended operation.
• Successful operation of integrated control systems to extract valuable human machine interface (HMI)-housed
operating data for future automation and process optimisation.
Successful campaign validates sustained parallel operation of three FJH units and advances scale-up program
*Prepared feed material refers to feedstock following preprocessing and upgrading. Depending on feedstock type, the mass reporting to the FJH reactor may represent only a
fraction of the original incoming material.
2
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
Figure 1: Commissioning Team
Managing Director & CEO Michael Walshe commented: “The successful completion of our first multi-unit FJH operations
campaign represents an important milestone in the development of our FJH technology platform. While the campaign was
intentionally focused on mechanical performance, fluidisation behaviour and process control rather than chlorination
chemistry or metal recovery, successful sustained operation of three units simultaneously provides valuable confidence in
the scalability of the technology and generates important engineering data for future development programs.
“Importantly, the campaign achieved 83% availability and approximately 100% utilisation during active operation, exceeding
our internal expectations for a first multi-unit commissioning campaign. While the campaign utilised inert test media, the
operating rates demonstrated were broadly consistent with processing reactor feed volumes derived from several tonnes
per day of incoming commercial feedstocks following preprocessing and upgrading. This provides highly encouraging
early evidence of the scalability of the platform and the suitability of the FJH architecture for larger-scale deployment.
“The campaign demonstrates our ability to operate multiple FJH units in parallel and establishes a strong foundation for
the next phase of development, which will involve multi-unit chlorination campaigns and metal recovery testing using
commercial feedstocks. Receipt of the chlorination permit for our interim testing facility is expected to represent the next
major scale-up milestone for the FJH program and will allow commencement of multi-unit reactive commissioning
campaigns involving catalytic converter scrap and electronic waste-derived feedstocks."
METALLIUM’S FJH TECHNOLOGY DEVELOPMENT ROADMAP
Metallium utilises the Technology Readiness Level (TRL) framework to assess and communicate the maturity of its FJH
technology platform. The TRL framework, originally developed by NASA and now widely adopted by U.S. Government
agencies including the Department of War (DoW), Department of Energy (DOE) and other federal funding agencies, provides
a structured methodology for evaluating technology development and scale-up risk.
• Metallium's technology development roadmap is deliberately structured as a layered and parallel, stage-gated
program that simultaneously advances field, laboratory and desktop development activities. The program currently
utilises multiple reactor prototypes and focuses on advancing the technology across several dimensions including
mechanical functionality, materials of construction (MOC), reactionary kinetics, production optimisation and end-
to-end operability.
• This particular campaign utilised inert feed material and a nitrogen atmosphere to evaluate and advance reactor
mechanical functionality, MOC integrity and operational confidence. Substantial learnings were generated through
evaluation of reactor fluidisation behaviour, instrumentation, controls, material handling systems and multi-unit
operating procedures under sustained operating conditions.
3
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
• Importantly, the campaign was designed to validate the operating platform rather than metallurgical performance.
The successful completion of the campaign provides an important data set supporting progression through TRL 5
and toward TRL 6, which focuses on integrated system validation under relevant operating environments.
• The next stage of development will involve implementation of minor design modifications, instrumentation
upgrades and calibration improvements, followed by multi-unit chlorination campaigns incorporating commercial
feedstocks, chlorine and proprietary catalysts.
• As a broad guide, TRL 8 is expected to correspond with demonstration-scale operation at Metallium's Texas
Technology Campus, while TRL 9 represents full commercial deployment and technology transfer to additional
operating sites.
Next Steps – Multi-Unit Chlorination Metal Recovery Campaigns
The successful completion of the multi-unit operations campaign represents an important precursor to the Company's next
phase of development. Metallium will now progress a series of parallel reactor optimisation, chlorination and commercial
feedstock campaigns across its portfolio of bench-scale and commercial-scale reactor systems. This approach is designed
to accelerate technology maturation while continuing to improve reactor performance, operating efficiency and production
capability.
Metallium's primary reactor development building is currently undergoing roof replacement works following the
identification of structural deficiencies. To maintain development momentum, the Company constructed and commissioned
an interim testing facility, which successfully hosted the multi-unit operations campaign. The Company has submitted
amendments to its existing permitting framework to allow chlorination activities to be conducted within the interim testing
facility. Metallium is currently working with the relevant regulatory authorities and expects the permitting process to be
completed in the coming weeks. Receipt of the chlorination permit represents the next major scale-up milestone for the
FJH program and will enable commencement of multi-unit reactive commissioning campaigns.
Upon receipt of the necessary approvals, the Company intends to commence multi-unit chlorination campaigns at its TTC
on commercial feedstocks, including catalytic converter scrap and electronic waste-derived materials. In parallel, chlorinated
bench scale and desktop assessment continue to progress to continually improve Metallium’s reactor technology.
These multi-unit chlorination campaigns will represent the first opportunity to evaluate chlorination chemistry, metal
recovery performance and process optimisation across multiple operating units simultaneously. The campaigns are
expected to generate important data relating to:
• Multi-unit chlorination performance.
• Product recovery and purity.
• Reagent utilisation and process economics.
• Throughput optimisation.
• Commercial operating parameters.
• Product qualification activities.
4
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
Figure 2: FJH Reaction System
Metallium’s Next Key Scale-Up Milestones
FJH Broad Iterative Development Pathway
✓ Single-unit operation
✓ Multi-unit inert commissioning
► Multi-unit chlorination commissioning (expected in coming weeks, subject to permitting)
► Commercial feedstock campaigns
► Demonstration-scale operation
► Commercial deployment
This announcement has been authorised for release by the Board of Directors of Metallium Limited.
For further information, please contact:
Michael Walshe
Managing Director & CEO
Metallium Ltd
info@MetalliumInc.com | +61 8 6391 0112
Andrew Keys
Investor Relations & Corporate Communications
Keys Thomas Associates
Andrew.keys@keysthomas.com | +61 400 400 380
5
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
ABOUT METALLIUM LIMITED
Metallium Ltd (ABN 27 645 885 463), is pioneering a low-carbon, high-efficiency approach to recovering critical and precious metals
from mineral concentrates and high-grade waste streams. The company’s patented Flash Joule Heating (FJH) technology enables the
extraction of high-value materials, including gallium, germanium, antimony, rare earth elements, and gold — from feedstocks such as
refinery scrap, e-waste, and monazite.
Aligned with U.S. strategic supply chain objectives, Metallium has recently secured its first commercial site in Texas via its wholly owned
subsidiary, Flash Metals USA Inc., marking a major step toward near-term production and revenue generation.
To learn more, visit:
Website: metalliuminc.com
Contact: info@metalliuminc.com | +61 8 6391 0112
Investor Hub: investorhub.metalliuminc.com
𝕏 x.com/Metallium_MTM
www.linkedin.com/company/metalliumltd
USA Office: 12 Greenway Plaza, Suite 1100, Houston, Texas USA 77046
Australia Office: Unit 4, 22 Railway Road, Subiaco, Western Australia
FORWARD-LOOKING STATEMENTS
This announcement contains forward-looking statements concerning Metallium Limited (Metallium or the Company), including
statements regarding the planned deployment of additional FJH reactors, the targeted Stage-1 PCB processing capacity of
approximately 8,000 tpa, potential throughput uplift relative to original internal design assumptions, expected scale-up of the FJH
platform, anticipated commercial deployment activities, and the Company's future plans, strategy and objectives.
Forward-looking statements can generally be identified by the use of words such as “may”, “will”, “expect”, “intend”, “plan”,
“estimate”, “anticipate”, “believe”, “target”, “forecast”, “project”, “potential”, “continue”, “should”, “seek”, and similar expressions.
These statements are based on information available to Metallium as at the date of this announcement and on assumptions and
expectations that the Company considers to be reasonable as at that date, including assumptions regarding: continued successful
operation and reliability of the FJH reactor platform; the availability and characteristics of suitable feedstock; the timing and outcome
of ongoing commissioning and optimisation activities; the availability of capital, equipment, personnel, services, regulatory approvals
and site access required for the planned multi-reactor deployment; the absence of material adverse changes in commodity prices,
exchange rates, input costs and general economic and market conditions; and continued progress of customer, partner and offtake
discussions.
Forward-looking statements are not guarantees or predictions of future performance and involve known and unknown risks,
uncertainties and other factors, many of which are beyond the Company's control. Actual results, performance or achievements may
differ materially from those expressed or implied by the forward-looking statements. Such risks and uncertainties include, but are
not limited to: technology scale-up and commissioning risk; feedstock supply, grade and recovery variability; processing throughput
and yield variability; capital and operating cost variability; financing risk; regulatory, permitting and environmental risk; intellectual
property risk; reliance on key personnel, contractors and partners; competition; and broader macroeconomic, market and geopolitical
conditions.
Production targets, processing capacity targets, throughput indications and timelines referred to in this announcement (including
the Stage-1 ~8,000 tpa PCB processing target and references to throughput uplift relative to original internal design assumptions)
are targets only. They are not production forecasts and are subject to the assumptions, risks and uncertainties described above.
There is no guarantee that these targets will be achieved, in the timeframes indicated or at all.
Investors should not place undue reliance on forward-looking statements. Except as required by the ASX Listing Rules, the
Corporations Act 2001 (Cth) and applicable law, Metallium does not undertake any obligation to update or revise any forward-looking
statement, whether as a result of new information, future events or otherwise.