Texas Technology Campus Update: Chlorinated Testing to Resume
and First Revenue Commences
▪ Site footprint and associated permitting constraint resolved at Texas Technology Campus ‘Gator Point’,
enabling chlorinated testing to recommence this week ahead of the planned 12-hour multi-reactor campaign in
September 2026
▪ Gator Point build-out continues, with the Area 140 roof restoration on track for completion in early September
and expanded XRD and TGA laboratory capability to support FJH optimisation and advanced materials testing
▪ Preparations underway for the ECT MXene testing campaign, with the first US$500,000 ECT payment underway
and full receipt expected by the end of this week, marking commencement of revenue from the MXene program1
▪ John Campo appointed Texas-based Head of Engineering, bringing approximately 30 years’ experience
including senior roles with BHP Billiton Petroleum, Celanese and Rohm and Haas (now Dow).
Metallium Limited (“Metallium” or the “Company”) (ASX: MTM; OTCQX: MTMCF; OTCQX ADR: MTLMY) provides the
following update on activities at its Gator Point Technology Campus in Anahuac, Texas, including the recommencement
of chlorinated Flash Joule Heating (FJH) testing, first revenue from the ECT MXene testing program1
, expansion of on-
site laboratory capabilities and continued development of the campus.
Managing Director & CEO Michael Walshe commented: "With the site constraint now resolved, we can recommence
chlorinated testing and continue progressing the FJH platform toward commercialisation. Our immediate focus is the planned
12-hour multi-reactor campaign in September.
“I would particularly like to thank Chambers County and the Chambers County Landfill for working constructively with us to
reach a practical solution. Their support has been greatly appreciated and reflects the strong relationship we are continuing
to build with the local community.
“We are also continuing to expand the capability at Gator Point. The Area 140 roof is nearing completion, we are adding
further analytical capability to our on-site laboratory, and preparations are underway for the ECT MXene testing campaign.
The first US$500,000 ECT payment is also underway, with full receipt expected by the end of this week. John Campo’s
appointment as Head of Engineering further strengthens the team as we continue to develop and scale the FJH platform”.
CHLORINATED TESTING AND SITE UPDATE
Metallium secured the required regulatory approval in December 2025 to support pilot-scale chlorination testing at Gator
Point. Following remedial works to the roof of Area 140, the planned installation location for the Company’s test reactors
was relocated closer to the northern boundary of the site (buildings 706, 707 & 708, see Fig.2). A subsequent permitting
review identified that the revised footprint did not provide the required separation distances from the northern property
boundary and nearest public receptor. Metallium subsequently worked with the neighbouring Chambers County Landfill and
the Texas Commission on Environmental Quality (“TCEQ”) to resolve the issue.
On 25 August 2026, the Company secured additional land immediately north of Gator Point, resolving the separation-
distance constraint and enabling Metallium, through its subsidiary Flash Metals USA, to recommence chlorinated
commissioning and testing in buildings 706, 707 & 708.
1
See ASX:MTM announcement dated Aug 4th
2026, ‘First Commercial FJH Technology Services Agreement’
2
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
The additional land has been secured from Chambers County for nominal consideration of US$1, with Metallium to receive
the County’s electronic scrap for processing through its planned Information Technology Asset Disposition (“ITAD”) centre.
The agreement expands the Gator Point site footprint and builds on the Company’s existing relationship with Chambers
County and the local community.
Figure 1: Gator Point site footprint, including newly leased parcel (blue) and future optional expansion area (red). Satellite imagery
predates recent site development
Chlorinated Testing to Recommence
Chlorination is a key element of Metallium’s FJH metals recovery platform. During FJH treatment, chlorine can react with
target metals to form metal chlorides with different physical and chemical properties, enabling their selective separation
and recovery. Metallium has demonstrated this approach across a range of metals and feedstocks, including gallium,
germanium and rare earth elements. The FJH platform can also utilise other halogens and halogen-based chemistries,
providing flexibility to tailor processing conditions to different metals and feedstocks.
Chlorinated testing is scheduled to recommence this week, followed by an approximately two-week ramp-up period. The
next major development milestone is the planned 12-hour multi-reactor chlorinated campaign, targeted for September
2026 in building 706. The campaign is expected to generate operating, process and environmental data to support:
• optimisation of reactor operating parameters and configuration;
• air-dispersion modelling and environmental assessment for longer-lead permitting applications; and
• engineering and design work for the next stage of FJH scale-up and commercialisation.
Engineering, testing and permitting activities will continue to progress in parallel.
3
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
ECT MXENE PROGRAM AND FIRST REVENUE
Preparations are underway for the ECT MXene testing campaign at Gator Point, which will utilise Metallium’s FJH reactor
platform and on-site technical capabilities to support the development and testing of MXene production using FJH.
Metallium has commenced receiving the first US$500,000 payment from ECT under the recently announced engineering
services and MXene development program, marking the commencement of revenue under the agreement. Due solely to
daily banking transfer limits, the payment is being received in tranches, with the full US$500,000 expected to be received
by the end of this week.
The program is being supported by the expansion of Metallium’s analytical capability at Gator Point, allowing testing, analysis
and process development activities to be undertaken within the Company’s technology campus.
MXenes are an emerging class of advanced two-dimensional materials with a combination of high electrical conductivity,
large surface area and tunable surface chemistry. These properties are driving growing research and commercial interest
across applications including defence, electromagnetic interference (EMI) shielding, electronics, thermal management,
sensors and next-generation energy storage.
MXenes are typically produced from precursor materials known as MAX phases. The ECT program will evaluate the
application of Metallium’s FJH technology to MXene production, with a focus on evaluating its potential as a faster and more
scalable processing route.
EXPANDED ON-SITE LABORATORY CAPABILITY
Metallium is expanding its on-site analytical capability at Gator Point, with additional equipment including X-ray diffraction
(XRD) and thermogravimetric analysis (TGA). The equipment will support both the ECT MXene program and ongoing
optimisation of the FJH reactor platform.
The expanded laboratory capability will allow more analysis to be undertaken directly at Gator Point, providing the technical
team with faster access to results and reducing the time between testing, analysis and reactor optimisation.
SAFETY AND OPERATING READINESS
Metallium has continued to strengthen its safety and operating systems at Gator Point ahead of recommencing chlorinated
testing. This includes enhanced operating procedures and engineering controls, a dedicated emergency response plan, site-
wide alarms, live incident and safety reporting, the appointment of two experienced safety professionals, engagement with
local emergency response stakeholders, and independent safety and technical reviews.
The Company has also undertaken audits and engagement with chlorine suppliers as part of its operating readiness activities.
AREA 140 ROOF
Despite weather-related disruptions, the Area 140 roof remains on track for completion in early September 2026.
Completion of the roof will allow the Company to progress remaining infrastructure works within Area 140 and the adjacent
development of Area 110.
4
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
Figure 2: Texas technology campus - July 2026
Figure 3: Area 140 Roof – August 2026
5
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
HEAD OF ENGINEERING APPOINTMENT
Metallium has appointed John Campo as Head of Engineering, based in Texas, strengthening the Company’s engineering
capability as it progresses the development and scale-up of the FJH technology platform.
John brings approximately 30 years of engineering and operational experience across chemical, refining and process
manufacturing environments, including senior engineering and strategic project leadership roles with Pinnacle Reliability,
BHP Billiton Petroleum, Celanese and Rohm and Haas (now Dow). He is a licensed Professional Mechanical Engineer in
Texas.
His experience spans greenfield plant development, process optimisation, reliability, technology testing and complex project
execution.
At Metallium, John will lead the engineering function with responsibility for engineering standards, reactor and process
integration, contractor management, technical assurance, project execution and operational readiness.
This announcement has been authorised for release by the Board of Directors of Metallium Limited.
For further information, please contact:
Michael Walshe
Managing Director & CEO
Metallium Ltd
info@MetalliumInc.com | +61 8 6391 0112
Andrew Keys
Investor Relations & Corporate Communications
Keys Thomas Associates
Andrew.keys@keysthomas.com | +61 400 400 380
ABOUT METALLIUM LIMITED
Metallium Ltd (ABN 27 645 885 463), is pioneering a low-carbon, high-efficiency approach to recovering critical and precious metals
from mineral concentrates and high-grade waste streams. The company’s patented Flash Joule Heating (FJH) technology enables the
extraction of high-value materials, including gallium, germanium, antimony, rare earth elements, and gold — from feedstocks such as
refinery scrap, e-waste, and monazite.
Aligned with U.S. strategic supply chain objectives, Metallium has recently secured its first commercial site in Texas via its wholly owned
subsidiary, Flash Metals USA Inc., marking a major step toward near-term production and revenue generation.
To learn more, visit:
Website: metalliuminc.com
Contact: info@metalliuminc.com | +61 8 6391 0112
Investor Hub: investorhub.metalliuminc.com
𝕏 x.com/Metallium_MTM
www.linkedin.com/company/metalliumltd
USA Office: 12 Greenway Plaza, Suite 1100, Houston, Texas USA 77046
Australia Office: Unit 4, 22 Railway Road, Subiaco, Western Australia
6
ASX: MTM | OTCQX: MTMCF and MTLMY (ADR)
FORWARD-LOOKING STATEMENTS
This announcement may contain forward-looking statements concerning Metallium Limited (“Metallium” or the “Company”),
including statements regarding the Company’s plans, strategies, objectives, expectations, intentions, future activities, development
and commercialisation programs, operations, technology, projects, regulatory and permitting activities, commercial arrangements
and anticipated outcomes.
Forward-looking statements can generally be identified by words such as “may”, “will”, “expect”, “intend”, “plan”, “estimate”,
“anticipate”, “believe”, “target”, “forecast”, “project”, “potential”, “continue”, “should”, “seek” and similar expressions. These
statements are based on information available to the Company as at the date of this announcement and on assumptions and
expectations that the Company considers reasonable at that date.
Forward-looking statements are not guarantees or predictions of future performance and involve known and unknown risks,
uncertainties and other factors, many of which are beyond the Company’s control. These include, without limitation, technology
development, scale-up and commissioning risk; operational and technical risk; feedstock supply and variability; capital and operating
cost variability; financing risk; regulatory, permitting and environmental risk; intellectual property risk; reliance on key personnel,
contractors, customers and commercial partners; market and commodity price risk; and broader economic, market and geopolitical
conditions.
Actual results, performance or achievements may differ materially from those expressed or implied by forward-looking statements.
Any anticipated outcomes, targets, estimates or timelines referred to in this announcement are indicative only and are subject to the
assumptions, risks and uncertainties described above. There is no guarantee that they will be achieved in the timeframes indicated
or at all.
Investors should not place undue reliance on forward-looking statements. Except as required by the ASX Listing Rules, the
Corporations Act 2001 (Cth) or other applicable law, Metallium does not undertake any obligation to update or revise any forward-
looking statement as a result of new information, future events or otherwise.
Share your feedback
Discover